Skip to main content
Solved

Unable to edit a calculation schedule

  • March 6, 2024
  • 1 reply
  • 36 views

I have created a calculation on charts and also created a schedule for it to run periodically. All is good so far. What I want to do now is to edit that schedule but can’t seem to be able to do that.

This is a screenshot of the page where I am hoping to be able to access my schedule from. There is no ellipsis for me to click on like there is on the top calculation in the list

Also, if I open the calculation I see this. For a new calculation, the “Running on schedule” button is “Save and schedule”. For existing schedules, though, only see the “Running on schedule” and nothing happens when you click on it.

So, my question is this: is there any way to edit an existing schedule?

Best answer by Arun Arunachalam

Hei hei 



Unfortunately as of today there is not a way to edit scheduled calculations so you would need to delete and recreate them. We do have this in the roadmap in the months to come. 

View original
Did this topic help you find an answer to your question?

1 reply

Arun Arunachalam
Seasoned Practitioner

Hei hei 



Unfortunately as of today there is not a way to edit scheduled calculations so you would need to delete and recreate them. We do have this in the roadmap in the months to come. 


Reply


Cookie Policy

We use cookies to enhance and personalize your experience. If you accept you agree to our full cookie policy. Learn more about our cookies.

 
Cookie Settings